Athletics

Updated February 15, 2019

Gyms
Program/Design  November 2017 - April 2018
Construction Doc  May 2018 - February 2019
Bidding  March 2019 - April 2019
Construction  June 2019 - September 2020

 

Stadium/Pressbox Complex
Program/Design  December 2017 - April 2018
Construction Doc  May 2018 - February 2019
Bidding  March 2019 - April 2019
Construction  June 2019 - May 2020
 
Demo  Natatorium  June 2019
Remove 4  Portables  June 2020
Remove Turf  Winter 2017/Spring 2018


AHHS Pool
Demolition  March 2019






AHISD welcomes patrons comments on any of the facility drawings.
Please email Mike Hagar at mikeh@ahisd.net