Kitchen/Classroom Addition/Commons

Updated February 18, 2019

Kitchen/Classroom Addition
Program/Design  June 2017 - August 2017
Construction Doc  September 2017 - March 2018
Bidding  April 2018 - May 2018
Construction  June 2018 - August 2019
 
Install 4 Portables  May 2019 - June 2019



Progress
March 22, 2019 - Concrete Masonry Units (CMU) continue to be installed.  Blue air barrier and masonry ties are being installed in preparation for brick veneer.  Metal studs are being installed in classroom spaces.  Roof work has commenced.  Mechanical air handling units are in place.  Electrical conduit and ductwork installation continues.
 Image of AHHS Commons Construction  Image of AHHS Commons Construction  Image of AHHS Commons Construction
Image of AHHS Commons Construction  Image of AHHS Commons Construction  Image of AHHS Commons Construction
February 8, 2019 - Concrete masonry units are being installed around the perimeter of the building.  Concrete flatwork has started in the courtyard area.  Mechanical ductwork, fire sprinkler piping, and electrical conduits are being installed.  Concrete floors have received their initial polish. 

Image of AHHS Commons canopy framing   Image of AHHS Commons east side
Image of AHHS Commons canopy framing  Image of AHHS Commons CMU
Image of AHHS Commons ductwork  Image of AHHS Commons
Image of AHHS The Oaks Courtyard
January 2, 2019 - The concrete slab has been placed and the concrete columns have been poured. The majority of the steel framing has been erected.
 Image of AHHS Art Gallery Space Image of AHHS Art Porch Columns Image of AHHS Columns
Image of AHHS Crane   Image of AHHS Steel
December 2, 2019 - The metal deck is being installed at the floor deck in preparation for concrete placement.  Concrete column framework is in place and columns will be poured the first week in December.
 Image of AHHS construction    Image of AHHS construction
Image of AHHS construction   Image of AHHS construction
Image of AHHS construction
October 29, 2018 - The perimeter concrete beams have been formed and poured.  Steel is arriving on site and will be used to form the foundation.
 Image of AHHS Commons construction Image of AHHS Commons construction Image of AHHS Commons construction

Image of AHHS Commons construction Image of AHHS Commons Construction

September 28, 2018 - The first portion of the mud slab has been poured.  The second portion of the mud slab will be poured the first of October 2018.

Image of AHHS mud slab          Image of AHHS mud slab
Click pictures to expand



Image of AHHS Commons

Image of AHHS Commons

Image of AHHS Commons

Image of AHHS Commons

Image of AHHS Commons

Image of AHHS Commons

Image of AHHS Commons

Image of AHHS Commons

Image of AHHS Commons

Image of AHHS Commons

Image of AHHS Commons


AHISD welcomes patrons comments on any of the facility drawings.
Please email Mike Hagar at mikeh@ahisd.net

 