STEM Building

Updated January 9, 2019

Alamo Heights Junior School
Stem Building
Program/Design  November 2017 - February 2018
Construction Doc  March 2018 - May 2018
Bidding  June 2018 - July  2018
Construction  August 2018 - July 2019

 

Progress
March 22, 2019 - Exterior sheathing has been installed at building exterior.  Handrails and guardrails are in place.  Electrical conduit and ductwork is being installed.  Sheetrock has started in the classroom spaces.
 Image of AHJS Construction  Image of AHJS Construction
Image of AHJS Construction  Image of AHJS Construction  Image of AHJS Construction
February 8, 2019 - Steel stairs are being completed.  Elevator tower sheathing is underway.  Metal roof deck is in place.  Mechanical ductwork and fire sprinkler piping are being installed.
 Image of AHJS STEM Building
Image of AHJS STEM collaboration space     Image of AHJS STEM Scaffolding
Image of AHJS STEM stairs at elevator     Image of AHJS STEM Lab
January 9, 2019 - Second-floor slab has been poured.
 Image of AHJS Shop Spaces  Image of AHJS Elevator Tower
December 2, 2018 - Steel framing is underway. Underground utilities have been installed along the back side of the Fine Arts Building.  Sewer line has been trenched in the driveway and covered with a metal plate; work will be complete in December. 
 Image of AHJS construction  Image of AHJS construction
Image of AHJS construction  Image of AHJS construction
Image of AHJS construction Image of AHJS construction Image of AHJS construction
October 29, 2018 - The beams, elevator pit, and concrete slab have been poured. 
 Image of AHJS construction Image of AHJS construction
Image of AHJS

September 29, 2018 - The elevator pit has been excavated and is scheduled to be poured the first week in October, weather permitting.  The beams and concrete slab are scheduled to be poured October 20th.
Image of AHJS excavation and elevator pit
Click picture to expand




Image of AHJS Bond Update
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building


AHISD welcomes patrons comments on any of the facility drawings.