Woodridge Elementary

Updated August 29, 2019

Woodridge Elementary
New Gym
Program/Design  January 2018 - February 2018
Construction Doc  March 2018 - July 2018
Bidding  August 2018 - September 2018
Construction  October 2018 - May 2019


New Fine Arts
Program/Design  January 2018 - February 2018
Construction Doc  March 2018 - July 2018
Bidding  August 2018 - September 2018
Construction  July 2019 -May 2020
 
Demolish Gym  June 2019
Renovate Classrooms  June 2020 - August 2020

August 29, 2019 - Woodridge slab has been poured. Building framing is underway.  Mechanical ductwork is being installed.
 Woodridge Fine Arts framing of building  Woodridge Fine Arts framing of building
June 18, 2019 - New playground and new gymnasium are complete.  Demolition of south gym is underway.
 New Woodridge Elementary playground  Demolition of Woodridge Elementary gym
Demolition of Woodridge Elementary gym  Demolition of Woodridge Elementary gym
March 22, 2019 - New playground equipment is being installed.  Gymnasium flooring and striping has been installed.  Striping at covered play area has been installed. 
 Play equipment at Woodridge
Covered play area at Woodridge Gym at Woodridge

March 22, 2019 - Plywood panels are being installed in the new gym.  Site work in underway for the new playground.  Concrete under new covered play area is installed.  Basketball goals have been installed.  Tile is being installed in restrooms. Site drainage along Oakleaf is underway. 
 Image of Woodridge Construction  Image of Woodridge Construction  Image of Woodridge Construction
Image of Woodridge Construction  Image of Woodridge Construction
February 8, 2019 - Concrete masonry units have been installed at the gym.  Block filler is being installed on concrete masonry units.  Metal panel and brick installation continues on gym exterior.
 
Image of Woodridge Gym roof lines     Image of Woodridge block filler
Image of Woodridge of gym exterior  Image of Woodridge Gym framing

January 9, 2019 - The pre-engineered metal building frame for the Gym and the Covered Play Area have been erected.  Metal panel installation is underway on the Gym walls.  Amphitheater seating between existing gym and new gym is in place.  Water line installation is underway across the play field.
 Image of Woodridge Gym and Covered Play Area  Image of Woodridge Gym
Image of Woodridge Amphitheater   Image of Woodridge Utility Trench
Image of Woodridge Steps and Amphitheater
December 2, 2018 - Foundation for the new gymnasium has been poured.  The storm drain piping is being installed.  Grading preparation for the amphitheater seating between existing gym and new gym is underway.  The gymansium's Pre-Engineered Metal Building Frame was delivered last week.
Image of Woodridge Elementary construction
Image of Woodridge Elementary construction      Image of Woodridge Elementary construction
October 29, 2018 - Construction fencing is in place and contractor mobilized.Upper-gradee playground equipment has been removed. Building pad preparation for the Gym is underway.
 Image of Woodridge Elementary construction Image of Woodridge Elementary Construction
 Image of Woodridge Elementary construction Image of Woodridge Elementary construction
September 28, 2018 - Pending board approval, construction on the Fine Arts Building and Gymnasium should commence October 8th.  Work will start with the Gymnasium and covered play area. 
Image of Woodridge rendering of Gym     Image of Woodridge covered play area
Click pictures to expand
 
 
 



AHISD welcomes patrons comments on any of the facility drawings.
Please email Mike Hagar at mikeh@ahisd.net

 

Website by SchoolMessenger Presence. © 2019 West Corporation. All rights reserved.