Construction Timeline

Bond 2023 Logo with Blueprint Icon

Construction Schedules/Timeline


The work will be divided into three project packages.

Package One
Alamo Heights High School - construction May 2024 to August 2026
Central Office/Learning Center - construction June 2026 to April 2027
Excel Academy/Connects - construction May 2027 to December 2027

Package Two
Robbins campus (located next to Tennis Center/Natatorium and current home of Excel and 09 Academies)
Softball Field and Accessory Buildings - construction October 2024 to September 2025
Tennis Improvements- construction January 2025 to December 2025
Baseball Improvements- construction January 2025 to December 2025
Robbins Building Removal and New Parking Lot - construction January 2028 to June 2028
Cambridge - construction January 2025 to August 2026
Woodridge - construction June 2025 to August 2026
Plant Services - construction September 2025 to March 2026

Package Three
Howard Early Childhood Center - construction May 2026 to July 2027
Alamo Heights Junior School - construction April 2027 to June 2028

All dates slated for campus construction projects are subject to change due to factors like weather.


How will Bond 2023 construction affect my AHISD learner? 
(Note- the current year is the 2023-2024 school year as a point of reference)
Website by SchoolMessenger Presence. © 2024 SchoolMessenger Corporation. All rights reserved.