Bond 2023 Updates

Bond 2023 Logo with Blueprint Icon

Alamo Heights ISD voters overwhelmingly approved three bond propositions in May 2023. Bond 2023 will provide updated learning spaces at all campuses, continue to address safety and security, and allow the district to be better community partners with additional parking, improved traffic flow, and outdoor and meeting spaces for community use.

The work will be divided into three project packages. Planning for Package One began in summer/fall 2023. AHISD is committed to sharing regular updates about the design, planning, and construction phases during this exciting time for the district.

The new high school schematic design was shared at the January 2024 Board Meeting. Construction at AHHS is expected to last from May 2024 until August 2026.

Rendering of front of proposed AHHS building

Package One also includes the relocation of the Excel Academy and Connects program to the current AHISD Central Office and the construction of a new Central Office/Learning Center for our school community.


May 2025 


Another month in the transformation of AHISD!

At the AHHS Academic Building, steel erection continues moving toward the South wing. In the North and Central wings, crews framed walls on the first and second floors and began decking for the roof on the third floor. Next month marks one year of construction!

Over at the Visitors Bleacher Complex, the new North and South buildings are taking shape. Bleachers are ordered and will be delivered later this summer.

At the AHISD Athletic Complex at Robbins, crews are digging for electrical and plumbing for the locker room building.

At the May Board Meeting, Trustees approved Bartlett Cocke as CMAR General Contractor for Project 3 which includes construction at Howard Early Childhood Center and Alamo Heights Junior School. They also approved R.L. Rhode Contracting as contractor for a baseball construction project that includes bleacher and restroom renovations.

With the end of the school year, teachers at Cambridge and Woodridge packed up the classrooms that will be refreshed over the summer. Crews began working the Monday after school let out for the summer.



April 2025 


Construction is officially underway at the AHISD Athletic Complex at Robbins! Tree clearing and site grading has begun for the first project, a new softball field, located behind the tennis courts and natatorium.

Over at the Visitors Bleacher Complex, foundation has been poured for both structures - meeting/concession building and visitors locker room- and block walls are starting to go up. Next we’ll see piers drilled for the bleachers.

Steel work continues at the high school, with the Main Wing just about finished.

At the April Board Meeting, Trustees approved the GMP for work at Cambridge and Woodridge that begins this summer.

At the April Bond Council Meeting, members took a field trip that included a bus trip inside the construction fences at AHHS for an up close look at progress.

Also in April, Cambridge Principal Jana Hawkins shared construction logistics with the Bond Council and campus community.

Design work also continued this month for the new Howard Building with design team members touring area facilities and speaking with other early childhood centers across the state to gather ideas.




March 2025 


We continue to see incredible progress as the steel is erected for the new building! The steel work is moving from the “North Wing” to the “Main Wing” of the structure. Foundation is also being poured for the 2nd and 3rd floors of the North Wing side.

Over at the Visitor’s Bleacher Complex, the work remains low to the ground with pipes and electrical work, in anticipation of foundation pours for the new locker room in the coming weeks.

At the March Board Meeting, Trustees approved the GMP for 2 portables (4 classrooms) at Cambridge. Approval for the main work at Cambridge and Woodridge will be presented to the Board in April.

Next month, the first project at the AHISD Athletic Complex at Robbins will begin as permits were finalized and secured this month.

The first design meeting for the new Howard building also took place at the end of March with school staff meeting with architects from LPA to start the process.




Construction Schedules/Timeline


Bond construction will be divided into three project packages.

Package One
Alamo Heights High School - construction May 2024 to August 2026
Central Office/Learning Center - construction June 2026 to August 2027
Excel Academy/Connects - construction May 2027 to December 2027

Package Two
AHISD Athletic Complex at Robbins (located next to Tennis Center/Natatorium and current home of Excel and 09 Academies)
Softball Field and Accessory Buildings - construction January 2025 to December 2026
Tennis Improvements - construction January 2025 to December 2025
Baseball Improvements - construction January 2025 to December 2025
Robbins Building Removal and New Parking lot - construction January 2028 to June 2028
Cambridge Elementary School - construction March 2025 to 2027
Woodridge Elementary School - construction June 2025 to August 2026
Plant Services - construction September 2025 to May 2026

Package Three
Howard Early Childhood Center - construction May 2026 to July 2027
Alamo Heights Junior School - construction April 2027 to June 2028

Visit the Construction Timeline page to see how construction will impact AHISD learners.

All dates slated for campus construction projects are subject to change due to factors like weather.


Keeping the Community Informed

Regular bond construction updates will be provided at Board Meetings, in the School Views publication mailed to AHISD residents three times a year, on this website, and on district social media platforms.

Who’s involved
Committees - AHISD Board of Trustees and Building Committee; Campus committees; and Bond Community Council

Architect - LPA Design Studios
General Contractor - Bartlett Cocke General Contractors
AHISD Construction Manager- Mike Hager

Contact Us
Direct any questions about AHISD Bond 2023 to Construction Manager Mike Hagar.
Website by SchoolMessenger Presence. © 2025 SchoolMessenger Corporation. All rights reserved.