Bond 2023 Updates

Bond 2023 Logo with Blueprint Icon

Alamo Heights ISD voters overwhelmingly approved three bond propositions in May 2023. Bond 2023 will provide updated learning spaces at all campuses, continue to address safety and security, and allow the district to be better community partners with additional parking, improved traffic flow, and outdoor and meeting spaces for community use.

The work will be divided into three project packages. Planning for Package One began in summer/fall 2023. AHISD is committed to sharing regular updates about the design, planning, and construction phases during this exciting time for the district.

The new high school schematic design was shared at the January 2024 Board Meeting. Construction at AHHS is expected to last from May 2024 until August 2026.

Rendering of front of proposed AHHS building

Package One also includes the relocation of the Excel Academy and Connects program to the current AHISD Central Office and the construction of a new Central Office/Learning Center for our school community.


December 2025 


The most visible progress on the outside of the new AHHS building is the brick work which is now complete on the front and south side along Castano.

Framing for all classrooms is complete, hallway tile will start in mid January, and sheet rock is progressing in the Main and South wings.

At the AHISD Athletic Complex, the turf is laid out on the new softball field and bleachers are in progress. The brick is finished on the building that will house tennis and softball locker rooms, coaches offices, and meeting space. Over the break, power was connected from the natatorium.

Classroom refreshes continue at Cambridge and the next set of classrooms in Building 3 will be completed in February. Piers have been drilled for the additions to the cafeteria and new Central Plant. Kitchen/Cafeteria Renovations are now underway. The kitchen will not be in service until next school year. Meals will be brought in from an alternate location.

Fifth graders at Woodridge will spend the second semester in portables as work has begun on an addition and renovation to the fifth grade classrooms. Over the Winter Break, demolition of interior classroom walls began in the 5th grade hallway. The project will be completed by the start of the 2026-27 school year.

Design work continues for the Junior School and new Central Office/District Community Center.



November 2025 


It’s been dominating the view over AHHS for over a year, and now it’s no more. The tower crane was disassembled and removed in mid November!

Brick is complete on the North Wing and front of Main Wing and is in progress on the South Wing. Windows are installed on the first and second floors of North Wing and almost done in Main Wing. All offices and classrooms are framed in Main Wing and on the first and second floors of South Wing.

At the end of October, the golf simulators were installed in the golf space in the new Visitor's Bleachers Complex. It’s the first devoted space for golf at AHHS.

Tennis courts have been resurfaced at the AHISD Athletic Complex at Robbins. Shade covers have been installed and wind screens are ordered. Over at the softball field, the installation of the field is getting underway and turf is down in the batting cages and bull pens.

At the Mule Yard, restrooms and bleacher shade covers are complete and bleachers will be installed this month.

The next set of classroom refreshes is complete at Cambridge and the next group of classrooms is being renovated now. Work on the Central Plant continues.

Woodridge received portables in mid November in preparation of the renovation of the fifth grade wing. Fifth graders will spend the second semester in the portables.

During the Thanksgiving Break, hallway work was completed at Woodridge. Materials had been on order since the summer classrooms refreshes, and the remaining work was scheduled for the break for minimal impact to students and staff.



October 2025 


One of the most visible signs of construction at Alamo Heights High School will soon be no more. Coming up in November, the crane that has towered over Broadway over the past year will be removed.

Framing of classrooms, hallways, and offices is underway on all three floors of the new building. Sheetrock is being installed and some areas have the first coat of paint. Brick has been installed on the North Wing and half of the front of the Main Wing. Windows are being installed after brick work. Roofing is ongoing and will be completed in early 2026.

Tennis court resurfacing is underway at the Robbins Athletic Complex and work also continues on the softball field and locker room/meeting room space.

The Mule Yard project continues with all baseball upgrades expected to wrap up in November.

Classroom refreshes continue at Cambridge Elementary. The first set of classrooms in building 3 will be completed the first week of November.

Planning and design work is underway for both the Junior School project and new Central Office building.

The latest edition of On Location with Dr. Bashara highlights the new Visitor’s Bleachers Complex at Orem Stadium which opened earlier this fall.



Construction Schedules/Timeline


Bond construction will be divided into three project packages.

Package One
Alamo Heights High School - construction May 2024 to August 2026
Central Office/Learning Center - construction June 2026 to August 2027
Excel Academy/Connects - construction May 2027 to December 2027

Package Two
AHISD Athletic Complex at Robbins (located next to Tennis Center/Natatorium and current home of Excel and 09 Academies)
Softball Field and Accessory Buildings - construction January 2025 to December 2026
Tennis Improvements - construction January 2025 to December 2025
Baseball Improvements - construction January 2025 to December 2025
Robbins Building Removal and New Parking lot - construction January 2028 to June 2028
Cambridge Elementary School - construction March 2025 to 2027
Woodridge Elementary School - construction June 2025 to August 2026
Plant Services - construction September 2025 to May 2026

Package Three
Howard Early Childhood Center - construction February 2027 to July 2028
Alamo Heights Junior School - construction June 2026 to August 2028

Visit the Construction Timeline page to see how construction will impact AHISD learners.

All dates slated for campus construction projects are subject to change due to factors like weather.


Keeping the Community Informed

Regular bond construction updates will be provided at Board Meetings, in the School Views publication mailed to AHISD residents three times a year, on this website, and on district social media platforms.

Who’s involved
Committees - AHISD Board of Trustees and Building Committee; Campus committees; and Bond Community Council

Architect - LPA Design Studios
General Contractor - Bartlett Cocke General Contractors
AHISD Construction Manager- Mike Hager

Contact Us
Direct any questions about AHISD Bond 2023 to Construction Manager Mike Hagar.