Natatorium (Excel Academy)



Natatorium
Natatorium
Construction          November 2019 - December 2020

 


October 1, 2020 - The pool floor was poured at the end of September and the Natatorium is on track to open in December 2020.
Just need to add water!

Natatorium Pool Cement PourNatatorium Pool Floor Pour Prep
June 11, 2020 - Concrete block continues.  Steel framing is going up.  Metal building frame is being erected.
 Construction of Natatorium  Construction of Natatorium
Construction of Natatorium Construction of Natatorium
Construction of Natatorium  Construction of Natatorium
Construction of Natatorium  Construction of Natatorium
Construction of Natatorium  Construction of Natatorium
May 20, 2020 - Concrete block continues.  Steel framing is going up.  Metal building frame is being erected.
 Natatorium Front of Building with Steel  Natatorium Metal Building Frame over Pool
March 31, 2020 - Concrete has been poured in the locker rooms and administration areas.  CMU is underway.  Foundation work for the spectator seating is ongoing.  Basement "lid" is being formed. 
 Natatorium CMU Walls at Admin Area  Natatorium CPS Installing Gas Lines
Natatorium Elevated Slab at Bleachers  Natatorium Floor Protection for Polished Concrete
Natatorium Painting Structural Steel  Natatorium Preparing for Basement Lid Pour
February 18, 2020 - Pool excavation continues.  Basement walls are formed.
 Natatorium Basement Formwork  Natatorium Basement Formwork
Natatorium Pool Excavation
January 7, 2020 - Earthwork and pool excavation is underway.  
 AHHS Natatorium Earthwork  AHHS Natatorium Pool Excavation
Natatorium excavation
November 13, 2019 - Earthwork is underway.
Natatorium Earthwork
 