STEM Building

Updated August 29, 2019

Alamo Heights Junior School
Stem Building
Program/Design  November 2017 - February 2018
Construction Doc  March 2018 - May 2018
Bidding  June 2018 - July  2018
Construction  August 2018 - July 2019

 

Progress
August 29, 2019 -  New STEM Building is complete.
STEM Building Collaboration Area     STEM Building at AHJS
August 9, 2019 -  New renderings of AHJS STEM Building
 AHJS STEM Building rendering  AHJS STEM Building rendering
AHJS STEM Building renderings  AHJS STEM Building renderings
AHJS STEM Building renderings  AHJS STEM Building renderings
AHJS STEM Building renderings  AHJS STEM Building renderings
AHJS STEM Buildings renderings  AHJS STEM Building renderings
AHJS STEM Building renderings  AHJS STEM Building renderings
AHJS STEM Building renderings  AHJS STEM Building renderings
AHJS STEM Building renderings  AHJS STEM Building renderings
AHJS STEM Building renderings  AHJS STEM Building renderings
AHJS STEM Building renderings  AHJS STEM Building renderings
June 18, 2019 - Brick and metal building panel are being installed on the building exterior.  Ceramic tile is being installed in the restrooms and drinking fountain niches.  Science casework is being installed in classroom spaces.
 Exterior of STEM Building    Metal panel of exterior of STEM Building
Tile being installed in STEM Building  Science casework in STEM Building  Collaboration space in STEM Building
Stairs in the STEM Building     View to fields from STEM Building
April 30, 2019 - Sheetrock and ductwork installation is ongoing throughout the building. The dust collector for the STEM labs are in place.  Exterior weather barrier has been applied to building envelope. Concrete floor polishing and exterior wall cladding has begun.
 Sheetrock at STEM Building Ductwork at STEM Building Dust collector at STEM Building
Weather barrier at STEM Building Concrete polishing at STEM Building Wall cladding at STEM Building

March 22, 2019 - Exterior sheathing has been installed at building exterior.  Handrails and guardrails are in place.  Electrical conduit and ductwork is being installed.  Sheetrock has started in the classroom spaces. 
 Image of AHJS Construction  Image of AHJS Construction
Image of AHJS Construction  Image of AHJS Construction  Image of AHJS Construction
February 8, 2019 - Steel stairs are being completed.  Elevator tower sheathing is underway.  Metal roof deck is in place.  Mechanical ductwork and fire sprinkler piping are being installed.
 Image of AHJS STEM Building
Image of AHJS STEM collaboration space     Image of AHJS STEM Scaffolding
Image of AHJS STEM stairs at elevator     Image of AHJS STEM Lab
January 9, 2019 - Second-floor slab has been poured.
 Image of AHJS Shop Spaces  Image of AHJS Elevator Tower
December 2, 2018 - Steel framing is underway. Underground utilities have been installed along the back side of the Fine Arts Building.  Sewer line has been trenched in the driveway and covered with a metal plate; work will be complete in December. 
 Image of AHJS construction  Image of AHJS construction
Image of AHJS construction  Image of AHJS construction
Image of AHJS construction Image of AHJS construction Image of AHJS construction
October 29, 2018 - The beams, elevator pit, and concrete slab have been poured. 
 Image of AHJS construction Image of AHJS construction
Image of AHJS

September 29, 2018 - The elevator pit has been excavated and is scheduled to be poured the first week in October, weather permitting.  The beams and concrete slab are scheduled to be poured October 20th.
Image of AHJS excavation and elevator pit
Click picture to expand




Image of AHJS Bond Update
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building
Image of AHJS STEM Building


AHISD welcomes patrons comments on any of the facility drawings.
Please email Mike Hagar at [email protected]

 
 

 

Website by SchoolMessenger Presence. © 2024 SchoolMessenger Corporation. All rights reserved.