Construction Schedules/Timeline
The work will be divided into three project packages.
Package One
Alamo Heights High School - construction May 2024 to August 2026
Central Office/Learning Center - construction June 2026 to August 2027
Excel Academy/Connects - construction May 2027 to December 2027
Package Two
AHISD Athletic Complex at Robbins (located next to Tennis Center/Natatorium and current home of Excel and 09 Academies)
Softball Field and Accessory Buildings - construction January 2025 to December 2026
Tennis Improvements- construction January 2025 to December 2025
Baseball Improvements- construction January 2025 to December 2025
Robbins Building Removal and New Parking Lot - construction January 2028 to June 2028
Cambridge - construction March 2025 to 2027
Woodridge - construction June 2025 to August 2026
Plant Services - construction September 2025 to March 2026
Package Three
Howard Early Childhood Center - construction February 2027 to July 2028
Alamo Heights Junior School - construction June 2026 to August 2028
All dates slated for campus construction projects are subject to change due to factors like weather.